Kingsnorth 400kV Substation SGT1 & SR1

National Grid identified that the 400/132kV 240MVA Super Grid Transformer (SGT1) and 13kV 30+30MVAr Shunt Reactor (SHR1) at Kingsnorth Substation require replacement due to their condition.

The Works included detailed civil, primary, and secondary design and engineering, project management, SHEQ management, the removal of redundant in-situ SGT, Shunt Reactor, primary and secondary equipment, structures, foundations, and bund walls etc.

Procurement of materials and equipment, civil works, installation and commissioning of new primary equipment, protection and control modification works, LVAC upgrades, etc. During the replacement of the SGT, Shunt Reactor and primary switchgear, busbar disconnectors, line disconnectors and earth switches were refurbished.

Several challenges had to be overcome during the construction works, in particular contaminated ground, which had to be shipped from site for processing, causing significant delays to programme. The GTDS delivery team made a huge effort to make up the lost time, ensuring that the SGT and Shunt Reactor were stage 1 commissioned and energised on time.

SGT1 Before

SGT1 After

SR1 Before

SR1 After

info@gtds.co.uk
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram